Primavera P6 Professional 17.7 ✦ Verified & Essential

: Go to the File menu and select New .

: Click Finish to see your new project appear in the Projects tab. Building the "Pieces" of Your Schedule

: Go to the Resources tab on the left to define the labor, non-labor, or material "pieces" that will be assigned to your activities. Primavera P6 Professional 17.7

: Enter a unique Project ID and a descriptive Project Name .

: Select the Plan Start date. You can usually leave the "Must Finish By" date empty for now. : Go to the File menu and select New

: In the Activities window, right-click and select Add to create the specific tasks required for your project (e.g., "Design," "Approval," "Construction").

: Select the responsible party from your Organizational Breakdown Structure (OBS). : Enter a unique Project ID and a descriptive Project Name

: Select the appropriate EPS node (the department or category where the project belongs) and click Next .